OMG Connections
Logo

 

Issue 2 • Volume 3 • April 10

PROJECTS

Ogden's 12th Street Project Complete

12th Street Paver
Staker Parson Companies crews worked around the clock to complete construction along 12th Street, one of Ogden's busiest roads.

The 12th Street corridor in Ogden, Utah, is one of the city's most heavily traveled and has been a first-of-its-kind project for Staker Parson Companies.

Since October 2008, crews have worked night and day to complete construction on the corridor lined with local businesses, and in early March, the main and side streets were completed and open to the public. The road features a unique concrete surface and is a breakthrough project for Staker Parson in the Ogden area.

Liquid asphalt was expensive and scarce when the project was bid. The Utah Department of Transportation (UDOT) decided to pour a concrete surface instead, believing that it not only would be a more economical option, but also would provide a longer life for the road based on traffic volume. Staker Parson Companies retained a full-time public information manager who worked directly with UDOT's public information consultant to keep the public informed of daily activities so that they could easily avoid construction zones.

Along with the challenges of traffic control and maintaining access for businesses, one of the biggest project obstacles was installing a new mainline water system for Ogden City.

"The existing water line was installed long before anyone who worked on this project was around, including Ogden City and UDOT," said Jeff Davis, project manager. "We had to heavily rely on old, as-built drawings that were not always accurate. It took a good deal of field engineering and cooperation to ensure things worked."

Nearly 40,000 cubic yards of concrete were placed, after grade crews rotomilled 65,000 tons of asphalt that will be used by Staker Parson Companies as reclaimed asphalt pavement.

"This was a great project for us because it involved cooperation from every subcontractor and every division of our company," said Davis. "We relied on the experience and expertise of everyone involved to make this a successful project."

Key subcontractors included Craythorne Inc., Craig Sorensen Construction and Romero Construction. Landscaping, fencing and signs will be completed in the spring, and the project will be complete by April 2010.

 
IN THIS ISSUE
 
 



FEATURED ARTICLE

CORPORATE UPDATES

PEOPLE

SAFETY

LEVERAGING THE PORTFOLIO
COMMUNITY

AWARDS

PROJECTS COMPANY NEWS ENVIRONMENT

 

About Connections

Oldcastle Materials, Inc.
900 Ashwood Parkway, Suite 700,
Atlanta, GA 30338

(770) 522-5600
oldcastlematerials.com
unsubscribe

© 2010 Oldcastle Materials, Inc.