 |
|
Issue 2 • Volume 3 • April 10
PROJECTS
LS Jensen Construction & Ready Mix Replaces 100-Year-Old
Irrigation Siphon
By CJ Beardsley, project coordinator
 |
A Little Giant Steam Shovel digs a big ditch on east
side of the valley. (Thank goodness for progress!)
Photo courtesy of the Bitterroot Historical Society |
On Oct. 5, 2009, LS Jensen Construction & Ready
Mix (LSJ) entered into a contract with the Bitter
Root Irrigation District to install 560 linear feet
of 72-inch steel pipe siphon and associated
improvements for the Siphon 1 – Phase 1
Replacement Project North of Darby, Mont. The
original request for proposal included an additional
350 feet of 66-inch steel pipe and associated
improvements, which was deleted from the
contract due to lack of funding.
The project is being funded through a Montana
Department of Natural Resources and
Conservation (DNRC) loan and a DNRC American
Recovery and Reinvestment Act grant with
matching funds from the U.S. Army Corps of
Engineers. The irrigation district's history has been
continually plagued by lack of funding, causing
serious financial troubles including bankruptcy in
1916. As a result, contractors over time have been
affected, and this project was no different. The
irrigation district scrambled to collect 60 percent
of its water users' signatures by July 31, 2009, to
unlock the federal contributions and authorize the
loan of state funds for only the 72-inch pipe.
 |
| Brad Riley is the LSJ superintendent responsible for crew
and subcontractor productivity, maintaining schedule,
safety and quality control. Thank you Brad. |
According to the Bureau of Reclamation, construction
standards were not as high in the early 1900s as
they are today. Ultimately the irrigation system's
concrete structures – the 70 miles of canals and
the mile-long irrigation siphon pipes – are suffering,
jeopardizing structural integrity and potentially
causing a total loss of water
for 1,375 irrigators on the
16,665 irrigable acres. This also
includes possible damage to the
river system wetlands and the
adjacent U.S. Highway 93. LSJ's
phase one scope of work includes
replacing the intake structure
and the 72-inch steel pipe. Crews
demolished the existing intake
structure and siphon last year,
and the new intake and siphon is
still in progress.
It was not until Dec. 10, 2009,
that LSJ was notified that
the remaining funds for the
66-inch steel pipe had been approved, but by this
time valuable production time was lost, not to
mention the rescheduling of crews, equipment and
subcontractors. Even the best planned projects
can suffer due to unforeseeable conditions and
since the project bid was to place the pipe from the
bottom up and the 66-inch pipe was at the bottom,
pipe installation was postponed until approval was
received. At this point two months had passed.
With liquidated damages for this project at the
rate of $4,000 per each calendar day after
Mar. 15, 2010, (rate based on lack of supplying
irrigation water to more than 16,500 acres of
cropland – potentially crippling the local economy),
the construction team had no time to waste. To
date the project is back on schedule because of
due diligence, hard work and the ingenuity of our
management team and field personnel.
 |
| Crews are carefully taking the pipe to its final resting place
in this snapshot from the bottom of the steep slope. |
LSJ's success is attributed to our "unsung heroes"
in the field adapting, improvising and overcoming
the difficult challenges this project has presented.
Every year miles of pipe are installed, only this
time it involved some seriously steep terrain, a
1.5H: 1V slope for a portion of the project, the
remaining portion with 3H: 1V and 4H: 1V slopes.
The elevation difference from the inlet structure
to the connection at the bottom of the hillside is
260 feet. As a result, getting the pipe there took
some creativity, and it's going to take a lot more
than that to stop our talented, innovative field
personnel from finding a solution to any problem
because we are completing the project safely and
within budget.
After a recent site visit, Stan Dugdale, LSJ vice
president, congratulated the crews on a great job
keeping safe and making sure that the equipment
is used properly. To date, our crews have worked
without incident despite the potential risks of steep
slopes, winter conditions and pipe weights ranging
upward to 12,450 pounds.
There are a total of five phases, and LSJ hopes
to acquire the remaining four phases and
continue to be a part of the Bitter Root Valley
Community history.
|
|